Plan the replacement before the shutdown.
MAX-MV can be evaluated as an alternative for suitable installations using ABB medium-voltage drives or Siemens / Innomotics Perfect Harmony equipment. The assessment is based on the installed model, motor duty and plant interfaces. It is an engineered replacement project rather than an assumption that cabinets, cells or software are interchangeable.
The most useful starting point is a condition and interface review. Identify the equipment causing downtime, the parts that can remain in service and the process requirements that have changed. A documented replacement scope helps the owner, local integrator and INOMAX agree responsibilities before drawings and delivery dates are committed.
02 · Rating and cabinet selection
Power, voltage and current selection
Match the motor nameplate current, overload duty and site derating before confirming a model. The filters below help you compare the listed selections; final cabinet and option details are agreed for the project.
7 reference selections
No matching selection in this table. Send your motor data for engineering review.
Dimensions exclude top fans, bypass additions and service clearances. At 6.6 kV from 2,800 kW and 11 kV from 4,500 kW, add an 800 mm current-limiting cabinet with matching depth and height. Use the approved project drawing for the complete installation.
03 · Application fit
Application requirements that shape the package
Obsolete or difficult-to-support drives
Evaluate replacement where parts availability, repeated faults or service constraints affect the plant’s maintenance strategy.
Process or capacity changes
Review motor duty, control performance, cooling and protection when the existing process has changed from its original design.
Planned plant modernization
Coordinate drive replacement with DCS migration, switchgear work, energy assessment and the scheduled outage.
04 · Integration and options
Functions, accessories and engineering decisions
Check the motor and cable circuit for reuse
Review motor insulation condition, voltage, current, cooling, bearings, feedback and cable length/routing. The multilevel output does not automatically qualify every legacy motor or cable. Document the tests and any remedial work needed before energization.
Do not assume the old transformer can remain
The phase-shifting transformer is coordinated with the power cells, secondary voltages, winding arrangement, isolation and protection. Reuse requires a specific compatibility assessment. Include a new transformer in the comparison unless reuse has been technically approved.
Translate the controls into a tested interface list
Map every command, analog signal, alarm, trip, permissive and bypass status. Confirm communication protocol, scaling, local/remote authority and loss-of-communication response. Use the agreed list for both factory testing and site loop checks.
Create an executable outage plan
Check dismantling, transport access, foundation work, cable adaptation, protection settings, commissioning and the plant restart sequence. Identify prerequisites, responsible teams and an agreed contingency plan before the outage begins.
Define the equipment scope
| Configuration item | What to agree |
|---|---|
| Motor control and feedback | Motor technology, control mode and encoder interface where required |
| Bypass / isolation | Manual or automatic line bypass, isolation and switching interlocks; selected for the process |
| Control integration | Standard Modbus RTU / I/O; optional PROFIBUS DP or exact TCP/IP arrangement |
| Continuity options | Cell-bypass strategy, controller redundancy or standby drive as project-selected |
| Service package | Spare cells, fans, boards, commissioning and training scope |
05 · Electrical performance
Performance for a defined operating duty
| Performance item | Selection basis |
|---|---|
| Motor-control modes | V/F; V/F with feedback; sensorless vector; closed-loop vector |
| Overload capability | 120% for 120 s; 150% for 5 s, checked against selected configuration and duty |
| Frequency resolution | 0.01 Hz; resolution is distinct from motor-speed accuracy |
| Acceleration / deceleration | 0.1–3,600 s; set within motor and process limits |
| Inverter efficiency | 98.5%; excludes the phase-shifting transformer |
| Power factor | ≥0.96 at the specified operating conditions |
| Harmonic performance | THD ≤4% for 3–4.16 kV; ≤2% for 6–13.8 kV. Confirm measurement point, loading and network conditions. |
Confirm performance at the required motor duty, supply conditions and cooling arrangement. For regenerative or braking loads, specify the operating cycle so a suitable two- or four-quadrant power stage can be selected.
06 · Technical data
Installation, environment and maintenance
| Item | Requirement / configuration |
|---|---|
| Operating temperature | −10 to +40°C; higher temperature requires an approved cooling and derating plan |
| Humidity | 20–90% RH, non-condensing, as the installation basis; confirm higher-humidity configurations |
| Altitude | Provide the site elevation; above 1,000 m, review insulation, cooling and derating for the selected configuration |
| Storage | −40 to +70°C; dry, protected storage without condensation or outdoor exposure |
| Cooling and enclosure | Forced air or water cooling; IP31 standard, IP42 optional, custom IP54 |
| Control supply | 220 V AC, 3 kVA, 50/60 Hz; optional DC supply by project arrangement |
| Control interfaces | 3 analog inputs / 4 analog outputs; 8 digital inputs / 5 digital outputs; RS485 / Modbus RTU standard |
| Installation | Indoor electrical room; no explosive/corrosive gases, conductive dust or oil mist; keep cooling and service access clear |
Plan safe service access, delivery openings, foundation loading and separate power/control cable routes. Inspection intervals and replacement work follow the installed equipment manual and the site maintenance plan.
07 · Supplier and configuration comparison
Compare complete proposals on the same basis
| Comparison point | What to check |
|---|---|
| Existing ABB installation | Record the exact type code, ratings, motor data and installed options; assess each interface individually. |
| Existing Siemens / Perfect Harmony installation | Record the exact family and cell/transformer arrangement, cooling and control requirements; verify the complete replacement scope. |
| Proposed MAX-MV package | Issue the rating, cabinet drawing, retained/replaced equipment list, interface schedule and testing plan. |
| Commercial comparison | Compare installed cost, shutdown work, spares and service commitments on an equivalent scope. |
Ask each supplier to identify inclusions, exclusions and deviations. The selected rating, options, installation work, acceptance test and service responsibilities should be clear before comparing the final price.
08 · Customer applications
Relevant industrial project experience
Imported-brand substitution experience
Industrial modernization
INOMAX’s project experience includes imported-brand substitution work for Lianyuan Steel, Pangang, Shougang, Capital Airport and APP paper-industry applications. The exact installed model and replacement scope must be checked for each new project.
Discuss a comparable configuration with INOMAX. The motor, equipment scope and operating conditions are assessed separately for each project.
Practical project FAQ
Questions to resolve before ordering
6 questions
Is MAX-MV a direct drop-in replacement for ABB ACS580MV?
A suitable MAX-MV configuration can be evaluated, but a drop-in fit is not assumed. Compare the exact voltage, current, overload, motor, protection, controls, cooling, footprint and cable entry. A retrofit proposal should state what remains, what changes and what must be tested.
Can MAX-MV replace a Siemens or Innomotics Perfect Harmony drive?
The installed drive and application can be assessed for replacement. Provide the model and nameplate, single-line diagram, motor data and cabinet/interface drawings. The proposal should identify the transformer, power-stage, control and installation changes required.
Can I reuse the existing phase-shifting transformer?
Only after its secondary winding arrangement, voltages, phase shifts, isolation, capacity, condition and protection are checked against the proposed power stage. It should not be treated as a universal component shared by different drive families.
Are MAX-MV power cells interchangeable with another brand?
Do not assume cross-brand interchangeability. Mechanical fit, voltage/current capability, insulation, control interfaces, firmware and protective coordination can differ. Spare modules must be matched to the installed equipment and approved service procedure.
How can we shorten the site shutdown?
Complete the site survey, interface mapping, drawings and factory tests before the outage. Prepare transport and lifting, cable adaptations, foundations, tools and commissioning responsibilities in advance. The achievable shutdown duration depends on the actual scope and site readiness.
What should we send for the first retrofit review?
Send photographs of the old drive and motor nameplates, the single-line diagram, cabinet dimensions, fault history and the required operating duty. Add DCS interface information, cooling conditions and the intended shutdown window.
No matching question. Ask our application team.
Technical resources
Catalog, manual & project support
MAX-MV catalog
Ratings, dimensions, features and configuration options.
MAX-MV user manual
Installation, operation, control settings and maintenance.
Project-specific documents
Contact INOMAX for project records, drawings, certificates and test reports matched to your application.
09 · Start the conversation
Let’s define your next MAX-MV project.
Request a Retrofit Assessment
Share the installed drive model, motor data, fault history and shutdown target. We will help define the replacement scope.
Email: info@inomaxtechnology.com
Build your local MAX-MV business
Discuss the industries you serve, application-engineering support, training, commissioning and spare-parts planning. Commercial and service arrangements are defined for your market and projects.